Project Description: As part of the overall capital improvement project, the LFMP required the demolition of the existing terminals along with their combined 20 gates. Terminal includes a new 20-gate T-shaped central concourse, check-in space, baggage claim areas and main lobby.

Project Size (Gross Square Feet) and Type:

  • Terminal 913,956 Square Feet (LFMP LEED® Boundary)
  • Central Plant 
  • Control Tower
Owner:The City of Dallas
Developer: Southwest Airlines, Dallas
Architect: Corgan Associates, Dallas
MEP Engineer:  Jacobs, Dallas
General Contractor:  Hensel Phelps Construction Co., Dallas
Project Duration:  Begun 2011 and completion October 2018. 
USGBC LEED® Certification Level: Silver

Description of Project Services Provided:

Facility Performance Associates and AIR Engineering and Testing (both are Gerald Kettler Companies) were contracted and completed:

  • Energy Efficiency and LEED® Consulting
  • Commissioning of HVAC & R, lighting and building control systems, domestic water
  • Test Adjust and Balance
  • Air Quality Testing Before Occupancy
  • Consultation work with design engineers and architect to provide assistance with the energy simulation model process for LEED®
  • Creation of the schedules of maintenance requirements & frequency
  • Creation of the schedule for re-testing commissioned systems with blank test forms from the original commissioning plan.
  • Creation of the schedule for calibrating sensors & actuators.